A software company sets up $m$ number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of $m$ is equal to:\\
(1) 150\\
(2) 180\\
(3) 160\\
(4) 125